Draft GRR 90% complete |
6/08 |
Alternative Formulation Briefing (AFB) |
8/08 |
Passing lane analysis complete |
7/09 |
Detailed cost estimates for NED plan selection |
7/09 |
Calculate NED benefits |
7/09 |
Value engineering study complete |
5/09 |
Real estate report complete |
7/09 |
Cost risk analysis complete |
7/09 |
Alternative plan comparison/ranking |
8/09 |
NED plan selection |
8/09 |
Final draft mitigation plan complete |
6/09 |
Draft GRR/EIS independent technical review |
8/09 |
Draft GRR and EIS public/agency review |
9/09 - 11/09 |
External peer review of GRR and EIS |
9/09 - 11/09 |
Public/agency comment resolution |
11/09 - 1/10 |
External peer review comment resolution |
11/09 - 1/10 |
Final GRR and EIS preparation |
12/09 - 3/10 |
Final GRR and EIS forwarded to Headquarters, USACE |
3/10 |
Civil Works Review Board |
4/10 |
Final public and agency review |
4/10 - 6/10 |
Department/Agency decision |
7/10 |
Headquarters, USACE and Asst. Sec. Army, Civil Works (ASACW) processing |
7/10 - 9/10 |
Record of Decision signed |
9/10 |